M/s Electrosteel Integrated Limited (EIL), a subsidiary unit of Electrosteel Group, pioneer in DI Pipes market, intends to set up a 2.2 Million Ton Per Annum (MTPA) Integrated Steel Plant to produce 1.2 MTPA long product of steel, 0.27 MTPA commercial billet, 0.4 MTPA pig iron & 0.33 MTPA Ductile Iron Pipe. The proposed plant will be based on Coke Oven-Sinter Plant-Pellet Plant-Blast Furnace-Basic Oxygen Furnace- Billet Caster-Wire Rod Mill and Bar Mill.
Technology Supplier:
EIL has tied up with Chinese Consultancy Agency for Technology transfer based on successfully operating Integrated Steel Plant in various locations in China.
Raw Material Linkage:
The Group has been allotted Parbatpur captive mine block for coking Coal in Jharia coalfield, near Bokaro, Iron Ore mine at Kodolibad near Barajamda and mine block for non-coking coal at Northdhadu, all in the state of Jharkhand.
Plant Site:
The proposed project site is located in Chandankyari Block , Bokaro District of Jharkhand State. The nearest town Bokaro, on the western side, is 22 Kms away from the site. The land comprises mostly of barren, agricultural, and non-agricultural land with small undulation. Source for raw mater for the plant will be Damodar river and the proposed location of the in-take pump house will be near the bank of Damodar river, which is about 10 kms away from the plant site.
The nearest railway station Talgarea, which is about 12 kms away from proposed plant site, is having single line electrified traction system.
The railway link for the proposed plant is to be developed from the above railway line with a take off point at Shewbabudih station. |